Skip to content
Well 6/05-A-12·Synthetic North field
RLWIWireline·Vessel “Sea Falcon

Planning workspace — well 6/05-A-12, Shift sliding sleeve and log lower completion

Objective
Shift sliding sleeve and log lower completion
Success
SSD confirmed shut + memory log recovered to surface
Conveyance
Wireline / e-line
Working depth
2 240 m MD · 1 985 m TVD
Well status
Shut-in · 312 bar SITHP · low H2S

Toolstring

Build & validate the string

Toolstring / BHA
  1. 1Rope socketTerminates the wireline to the toolstring0.4 mOD 38 mm3 kg
  2. 2Stem (weight bars)Adds weight to overcome well pressure and friction3.6 mOD 41 mm62 kg
  3. 3Mechanical jarsDelivers up/down impact to set or free tools1.5 mOD 43 mm25 kg
  4. 4Knuckle jointFlexes the string through deviation and restrictions0.5 mOD 43 mm8 kg
  5. 5Shifting toolService toolService tool — engages and strokes the sliding sleeve1.2 mOD 43 mm18 kg
Tally (made-up length)7.2 m
Validation summary
Length
7.2 m
Weight
116 kg
Max OD
43 mm

Fit by restriction

  • Tubing hanger56 mm · pass
  • Sliding sleeve (SSD)3 mm · tight
Reachpasses (116 / 85.1 kg)Connectionsall compatible

Simplified demonstration heuristic — not a real torque-&-drag / friction model.

Fit: 1 tight. Reach: pass. Connections: ok.

Well schematic — planOD 43 mm
ReservoirSurface 0 m05001 0001 5002 0002 5003 000Tubing hanger 56 mm passSliding sleeve (SSD) 3 mm tight
Readiness gate7/8
  • ObjectiveReady
  • ToolstringReady
  • MethodReady
  • AssetsNeeds attention2 allocated tool(s) not cert-valid at mob date.
  • ScheduleReady
  • RiskReady
  • BarriersReady
  • CostReady
  • AuthorityPending2/4 signed, permit outstanding

1 engineering gate(s) still need attention.